PSEG Long Island LLC, on behalf of the Long Island Power Authority (LIPA), issued this Request for Information (RFI) on March 16, 2026, in response to New York State Public Service Commission (PSC) recommendations outlined in its Order Initiating Proceeding and Directing Reliability Contingency Plan. The RFI seeks to evaluate the prospects for developing renewable and non-emitting energy resources on Long Island to meet LIPA's resource requirements in future years.
The RFI invites respondents to submit information on a comprehensive range of renewable and non-emitting resource solutions. Areas of focus include demand-side management measures such as energy efficiency, load-shifting measures, demand response programs, and virtual power plants. Responses should also address distributed renewable resources and other non-emitting generation technologies. The information gathered will support LIPA's ongoing efforts to advance reliable, cost-effective, and sustainable energy strategies for Long Island.
Key Dates and Schedule:
- RFI Issuance: March 16, 2026
- Webinar: March 25, 2026 at 11:00 AM EPT with pre-registration link provided
- First Round Clarification Questions Deadline: March 27, 2026
- PSEG LI Responses to First Round Questions: April 6, 2026
- Second Round Clarification Questions Deadline: April 10, 2026
- PSEG LI Responses to Second Round Questions: April 17, 2026
- RFI Response Submission Deadline: April 30, 2026 at 5:00 PM EPT
Submission Instructions and Contact Information:
Responses and questions concerning this RFI should be directed to PSEG-LI-Non-EmittingResourcesRFI@psegliny.com. Respondents are encouraged to attend the webinar on March 25, 2026 for detailed discussion of the RFI requirements and to register via the provided Microsoft Teams link. Supporting documentation includes the full RFI document and an RFI Resource Data Workbook available for download.